Project Case | Sarawak, Malaysia
Ahead of schedule on the U012 road
Kapit Division, Sarawak — On 30 November local time, the U012 road Bailey bridge under Malaysia’s Baleh Hydroelectric Kapit Division Village Road Project was completed and opened to traffic ahead of schedule. The bridge was designed, manufactured and installation-guided by EVERCROSS BRIDGE TECHNOLOGY (SHANGHAI) CO., LTD., and erected by Sinohydro Bureau 7 Co., Ltd. of POWERCHINA. The completion marks an important milestone in the overall delivery of the project.
For the communities along the U012 road, the opening converts a daily bottleneck into a permanent crossing — one that no longer depends on river levels, weather or temporary works.
Seven bridges, 276.6 metres of steel truss
A total of seven Bailey bridges have been constructed along the Kapit Division Village Road Project, four of which are located on the marked sections of the U012 road, with a combined length of 276.6 metres. Each structure was engineered for its own crossing, while sharing the same modular truss system so that components, tooling and erection methods stay common across the programme.
Designed and manufactured to European and American standards
In strict accordance with the contract, all bridges were designed and manufactured to European and American standards. The designs passed successive rounds of review and approval during the design stage, and all structural components were inspected and tested by a third-party laboratory recognised by the Malaysian government during manufacturing, ensuring full compliance with the client’s quality and safety requirements.
Opened to traffic 30 days ahead of programme
The bridge works were completed 30 days ahead of the original schedule and successfully opened to traffic. Since opening, the bridges have resolved long-standing travel difficulties for local residents, significantly shortened journey distances, improved the efficiency of rural transport operations, stimulated the growth of local rural industries, and created additional income and employment opportunities for farming communities — delivering tangible social and economic benefits to the region.
The aerial view below shows the completed U012 crossing in service, with the road formation and approach embankments tied into the existing village track on both banks.

Delivered through Sarawak’s heat and heavy rain
The year 2024 was a critical period for the construction of the Kapit Division Village Road. Throughout the bridge works, the project team maintained high morale, coordinated effectively, organised construction meticulously, and optimised resource allocation. By implementing targeted measures, the team overcame multiple adverse conditions, including the local high temperatures and heavy rainfall typical of Sarawak’s tropical climate, and secured the construction schedule under exceptionally challenging conditions. The efficiency, quality and reliability of the works have been highly recognised by the local government and the project owner, laying a solid foundation for achieving the goal of completing the entire road by August 2025.
Project overview
| Project | Baleh Hydroelectric Kapit Division Village Road Project |
| Location | Kapit Division, Sarawak, Malaysia |
| Scope | 7 Bailey bridges; 4 on the U012 road, 276.6 m combined |
| Design and supply | EVERCROSS BRIDGE TECHNOLOGY (SHANGHAI) CO., LTD. |
| Erection | Sinohydro Bureau 7 Co., Ltd., POWERCHINA |
| Standards | European and American design and manufacturing standards; third-party laboratory testing recognised by the Malaysian government |
| Status | Opened to traffic on 30 November, 30 days ahead of schedule |