Project Case | Ethiopia
A two-week race against the rain
When the rainy season arrives in many parts of Ethiopia, unpaved crossings quickly become unreliable and site access can be cut off for weeks. On this project, the schedule mattered as much as the structure itself.
EVERCROSS BRIDGE TECHNOLOGY (SHANGHAI) CO., LTD. is pleased to announce the successful completion of a 39.624 m HD200 bailey bridge in Ethiopia. The bridge is a double-row single-layer reinforced (DSR) configuration, fully hot-dip galvanized, and was assembled on site in just two weeks — finished safely before the onset of the local rainy season. The client expressed strong satisfaction with both the product and the installation process.
Project overview
| Location | Ethiopia |
| Bridge type | HD200 modular bailey bridge (steel truss) |
| Configuration | Double-row single-layer reinforced (DSR) |
| Overall length | 39.624 m |
| Surface treatment | Full hot-dip galvanizing |
| Installation | Guided on site by 2 EVERCROSS engineers |
| Assembly period | 2 weeks (after client completed the piers) |
The substructure — the bridge piers — was built by the client’s local team. Once the piers were ready, our two field engineers arrived to provide full-time, on-site installation guidance, working alongside the local crew until the final panel was pinned and the deck was open.
Assembly with the HD200 panel system
The bridge uses the HD200 panel system, assembled in a double-row, single-layer reinforced (DSR) arrangement to give the 39.624 m structure the load capacity and stiffness required for regular traffic on this route.
Every panel, transom and brace is a standardized, interchangeable component connected by pins — with no site welding and no heavy lifting equipment. Ordinary local workers, trained and supervised by our engineers, assembled the bridge using hand tools. This kept the installation safe, controllable and independent of scarce specialist skills.
Full hot-dip galvanizing
The entire bridge was hot-dip galvanized. In a climate that combines intense rainy seasons with strong year-round sunshine, corrosion protection is essential: a fully galvanized structure delivers decades of service with near-zero routine maintenance. In addition, every modular component can be dismantled, relocated and re-erected on another crossing in the future — the bridge remains an asset for years to come.
Two engineers on the ground
EVERCROSS dispatched two experienced field engineers to Ethiopia to direct the assembly. Their role went beyond supervision: they trained the local installation crew step by step — panel erection, launching, deck installation and final alignment. When the next bridge is needed, the local team will already know how to build it.
Finished before the first rains
The client completed the piers, and from that moment the clock was running. Working steadily through a structured two-week program — panel assembly, launching, decking and inspection — the joint team closed the bridge before the first sustained rains arrived. Finishing on time protected the project budget and secured the traffic connection this bridge now serves.
A growing footprint in Africa
The successful completion of this project further strengthens EVERCROSS’s presence in the African market. Delivering a fully galvanized HD200 bailey bridge on schedule — and ahead of the rainy season — demonstrates that our modular steel bridge solutions are well suited to the region’s climate, terrain and construction conditions. More importantly, the local installation crew trained by our engineers can now build EVERCROSS bridges independently, laying a solid foundation for future cooperation in Ethiopia and across Africa.
Each project like this one adds to a growing base of trust between EVERCROSS and its African partners, and we look forward to supporting more communities across the continent with reliable, long-lasting steel bridge solutions.